1. Project Name: Iraq CPF Akkas
2. Introduction: Central processing facility and gathering system for non-associated gas.
3. Projected Contract Sum: US$708mn
4. Duration: First phase - 24 months from the start, Second phase - Completed by 2017.7.15
5. Implication:
- The first landing project in Iraq
- Secured advantageous location for potential large-scale constructions within Al Faw port
(Dry Bulk Terminal, Container Terminal, Marine Base and etc.)
- Established firm foothold into Iraq’s rebuilding market (Basrah New Town PJ, etc.)
|